Progress Summary (Oct 7 - Nov 18)
Completes Progress:
- Final target: 13,223 (per budget)
ⓘ
Overall project target number
- Expected progress (at 119.1/day x 28 days): 3336
ⓘ
Target number we should have reached by now (daily target × days elapsed)
- Current total: 382
ⓘ
Actual cumulative number achieved so far
- Current achievement rate: 11.5%
ⓘ
Achievement rate for current period (current total / expected progress)
- Progress to final target: 2.9%
ⓘ
Progress percentage towards final target (current total / final target)
- Current daily average: 14.0 completes/day
ⓘ
Average daily rate calculated using linear regression
- Gap from daily target: 105.2 completes/day
ⓘ
Difference between target daily rate and current daily rate
- Required catch-up rate: 154.7 completes/day
ⓘ
Daily rate needed from now to reach final target by deadline
Eligibles Progress:
- Final target: 2,729 (per budget)
ⓘ
Overall project target number
- Expected progress (at 24.6/day x 28 days): 688
ⓘ
Target number we should have reached by now (daily target × days elapsed)
- Current total: 91
ⓘ
Actual cumulative number achieved so far
- Current achievement rate: 13.2%
ⓘ
Achievement rate for current period (current total / expected progress)
- Progress to final target: 3.3%
ⓘ
Progress percentage towards final target (current total / final target)
- Current daily average: 3.4 eligibles/day
ⓘ
Average daily rate calculated using linear regression
- Gap from daily target: 21.2 eligibles/day
ⓘ
Difference between target daily rate and current daily rate
- Required catch-up rate: 31.8 eligibles/day
ⓘ
Daily rate needed from now to reach final target by deadline
Trend Projection Note:
- Projections (dashed lines) are based on all data from Oct 7 to Nov 18
- Recent daily rate changes may not be fully reflected in the long-term projection